Lost my Frontage and Car Park since i resisted to pay Rs.45000.
As per TNEB rule a new connection has to be installed within 11 days.
I was made to wait for 11 month. Myself and my relatives constructed a flat for our own use. Totally there are 9 flats and the total size is 9500 Sq.Ft. We applied for 10 new Connections. We were harassed by them and was misguided by them saying that we need to install a transformer for which we need to give space. At last after 11 months a transformer was erected right in front of my flat that to inside my place blocking 2 car parking space. The rule say only 12 flats or above 10000 Sq.Ft. need a transformer.