Completion plan for Occupancy certificate on residential plot other than group housing in Noida

Name should not be empty

How to get an Occupancy Certificate

1. The Building Completion plan prepared and signed by the Architect, registered with COA, when submitted shall be deemed as Occupancy Certificate. At the time of submission following documents need to be submitted-

 

(i) Declaration on Rs 10/- stamp paper duly signed by the Architect and allottee stating that the Building constructed by the allottee is constructed under the supervision of a Architect and is in accordance with a Zonal Plan and Building Regulations/ Directions applicable from time to time of Greater Noida Industrial Development Authority.

(ii) Two post card size photographs of building constructed (one front and one backside) duly attested by the Architect with date and plot number.

(iii) All the documents listed as per checklist A of Appendix-9 in Building Regulations-2002 and drawings with declaration stamped and signed.

 

2. On submission of the aforesaid papers the Authority shall give a receipt and receipt shall be deemed as occupancy/ completion certificate.

 

3. If at the time of scrutiny by the Authority (within one month of submission of drawings) any deviation from the drawings or Zonal Plan, Building Regulations/ Direction as applicable from time to time is found, architect signing the drawings shall be held responsible for the same.

 

4 If at the time of scrutiny by the Authority (within one month of submission of drawings) any mistake is found, architect signing the drawings shall be held responsible for the same.

 

5. Indemnity bond on Rs. 100/- stamp paper duly notarized indemnitying that construction shall be as per GNIDA Regulations,, Directions all as amended upto date and all other stipulation and requirements by the Authority from time to time by Architect & applicant.

 

6. Checklist for Completion duly filled. 

General Information

1. The cases in which sanction/ completion have been received will be scrutinized by the Authority.

 

2. In case mistake is found in drawing for sanction and date for completion action shall be taken against the Architect as per Greater Noida Industrial Development Area Building Regulation 2002.

 

3. If a Sanction/ Completion submitted with Authority is found against the Building Regulations, Planning and Development Directions and Zonal Plan, the Authority can cancel such plan. On cancellation of such plan lease holder or Architect shall not claim any damages against the Authority.

 

4. All Architects, registered with Council of Architecture, shall be issued a Record Book.

 

This Record book shall be issued on producing of following documents at Customer Relation Cell by Architect/ representative:-

  1. Original COA Certificate.
  2. Application form duly filled.​ 
  3. Any one of the original identity proof.
  • Voter I. Card.
  • PAN Card.
  • Driving License.

Further Architect will also submit duly self attested copy of aforesaid documents and signature & address of Architect Attested by Bank Manager.

The aforesaid orders are being issued with the approval of Chief Executive Officer and shall be implemented with immediate effect.
What's your reaction?